DAY 1 Because of its steel frame our unique base system requires minimal amount of digging. All that is required is a series of small concrete pads. |
|
|
DAY 2 The Speedy-Base is assembled leveled and bolted to the exterier wall of dwelling and modular walls are errected. |
|
|
DAY 3 Electrical and central heating pipes are installed in the modular walls. |
|
|
DAY 4 The conservatory windows, doors and roof are errected as in a conventional installation. |
|
|
DAY 5 Walls are dry lined ready for decorating. Floor installation and floor boards are laid.The brick backs are bonded in place ready for pointing. |